At the Youngsville City Council meeting on Sept. 10, 2026, development investor John Cazayoux described what he and his partners want to build on a 196.778-acre tract south of town. He said it would be roughly 600 homes priced from $250,000 to $1.3 million, on lots 55 to 120 feet wide. The ordinance needed to bring that land into the city split 2–2. Lindy Bolgiano and Nicholas Niland voted for it, Shannon Bares and Simone Champagne voted against, and Matt Romero was absent, so the motion failed. By the council's Nov. 12 meeting, the annexation was back on the agenda as Ordinance 520-2026.
The Guillot Road tract is one of several large projects that came before local boards around Youngsville this fall. Taken together, these subdivisions add up to more new homes than anything Youngsville has gone through since Sugar Mill Pond. The debates over them kept returning to entrances, traffic and the roads leading to each site. For a buyer choosing a home this winter, the pace of those roads matters more than the total number of homes.
The projects in play this fall
Here is the record on each project from the fall council and commission meetings.
| Project | Location | Jurisdiction | Size | Status |
|---|---|---|---|---|
| Highpointe Farms | 724 Austin Road | Unincorporated Lafayette Parish | 240 lots on 59 acres | Preliminary plat approved on appeal by the Parish Council, 3–2 |
| Evergreen Estates | 500 block of Piat Road | Lafayette Parish review | 213 lots on about 46 acres | Approved with conditions by the Parish Planning Commission in October |
| J&M Land Investments and S&C Developers tract | Guillot Road area | Annexation into Youngsville proposed | 196.778 acres, about 600 homes proposed | Annexation introduction failed 2–2 on Sept. 10; Ordinance 520-2026 was on the Nov. 12 agenda for public hearing |
| Burley Plantation, Phases 1A and 1B | Guillot Road | City of Youngsville | 65.06 acres total, 7,800 sq. ft. minimum lot | Preliminary plat approved Oct. 8, 5–0 |
| Bailey Grove | Chemin Metairie Parkway, south of the Youngsville Sports Complex | Presented to Youngsville council | 716 acres, about 1,600 homes | Presented April 10, 2025, with a 20- to 25-year buildout |
Highpointe Farms, Evergreen Estates, the Guillot Road annexation tract and Bailey Grove together come to about 2,650 proposed homes. That figure leaves out Burley Plantation and the next phase of Sugar Mill Pond. Phase 31's preliminary plat was tabled on Oct. 8 and placed on the Nov. 12 agenda. For scale, The Advocate reported that Sugar Mill Pond will cover just over 500 acres with 1,200 homes once it is built out. That neighborhood shaped much of the town over two decades, and the projects in the table above would add more than twice as many homes.
On Austin Road, the number of entrances drew the objections
Both parish-side projects come from Stillwater Development, and both went to the Lafayette Parish Planning Commission in October. On density alone, the results look backward. Evergreen Estates plans 213 lots on about 46 acres, or roughly 4.6 lots per acre, and it was approved. Highpointe Farms plans 240 lots on 59 acres, or about four per acre, and the commission took no action, which counts as a denial.
Commission chair John Broussard explained the difference to Acadiana News First. "One case had 240 residential lots with only two entrances and egresses, and just the congestion that would have brung with over 480 vehicles – typically two vehicles per home," he said. He also cited concerns about the project's size and its drainage analysis.
The setting added to the debate. According to The Advocate, Highpointe Farms would sit next to Bicentennial Acres, just south of Ben Franklin Drive. Homes in Bicentennial Acres sit on two acres each, and Highpointe Farms would put four homes on each acre. More than a dozen Bicentennial Acres residents asked the Parish Council to reject the plat, citing drainage and traffic. The developer appealed anyway, and the council approved the preliminary plat 3–2, with Donald Richard and A.B. Rubin voting no.
So the two subdivisions with the highest densities on this list have both been approved, and in both votes the debate centered on traffic and drainage.
The largest plan runs on a 20-year clock
A vote is not a house. The Advocate reported that David Hensgens, who represented Highpointe Farms, told the council the developers want the opportunity to take the next steps, and that he has had numerous proposed developments receive plat approval that did not prove feasible later in the process.
Bailey Grove shows how long the largest of these projects can take. When Prescott Bailey of Young's Industries presented the plan to the Youngsville council in April 2025, he described 716 acres running from Decon Road to land next to Detente Road. The plan includes more than 100 acres of ponds, dog parks, playgrounds and a trail system open to the public, and it mixes single-family, multifamily and independent senior living. The developers hoped to seek approvals by the end of 2025 and break ground as early as 2026, and they expect the full buildout to take 20 to 25 years, with plats approved in phases.
Roads are on the city's own agenda too. The Nov. 12 council agenda included Resolution 2026-32, accepting partial substantial completion from Glenn Lege Construction on the South Larriviere Road, LA 92 and Chemin Metairie project. It also included Resolution 2026-33, which urges the state to prioritize, fund and expedite the roundabout and widening at LA 92 and LA 339, Verot School Road. Residents who drive Youngsville Highway have watched the same kind of change at the Fortune Road roundabout. Those are the same corridors the new subdivisions would feed into.
Guillot Road has two projects side by side
The Advocate reported that the Guillot Road land, owned by J&M Land Investments and just south of the city, had been in annexation talks since 2024. Council member Bolgiano, who voted for the annexation in September, put her reasoning this way: "This is going up either way. I'd rather we be the ones regulating since it's going to affect our people here in Youngsville the most."
Ordinance 520-2026 covers the J&M and S&C tracts together. Burley Plantation, also on Guillot Road, is already inside the city. Its preliminary map lists McLain Investments LLC as owner and applicant, a total development area of 65.06 acres, and a 7,800-square-foot minimum lot. The council approved its first two phases unanimously after questions about water pressure and sewer capacity.
Between them, Burley Plantation's 65 acres and the 196.778-acre tract put more than 260 acres of planned housing on one road at the south edge of town. The Austin Road and Piat Road projects sit outside the city in unincorporated Lafayette Parish, a setting we wrote about from the Broussard side in A Broussard Address, Two Rulebooks.
What this means for a home you buy this winter
The first thing to settle is what is planned for the open land around a property. A buyer touring near Austin Road, Piat Road, Guillot Road or Chemin Metairie Parkway can look up what has been filed nearby, because the hearings are public and the plats are posted in council agenda packets. Commission chair Broussard put it simply to Acadiana News First: "If you have concerns, show up or send in a memo."
The second is when you move in relative to construction nearby. A family buying in the first phase of a large subdivision moves in early and lives beside construction traffic for as long as the later phases are being built. At Bailey Grove, that could be 20 to 25 years. A family buying in an established subdivision near one of these sites gets new neighbors gradually, and the access roads get busier one phase at a time.
The third is price. Cazayoux's range of $250,000 to $1.3 million means the Guillot Road tract alone would add homes across nearly every price range in the Youngsville market. Owners of established homes would compete with that new construction over several years, and resale sellers already set their prices against builder incentives today. A slow pipeline gives those sellers more time to sell before the new supply arrives.
FAQ
Which of these projects are inside Youngsville's city limits? Burley Plantation's preliminary map places it in the City of Youngsville. The J&M and S&C tract on the Guillot Road side was proposed for annexation into the city this fall. Highpointe Farms on Austin Road is in unincorporated Lafayette Parish, and Evergreen Estates on Piat Road went through the Lafayette Parish Planning Commission.
Is Bailey Grove under construction? Bailey Grove was presented to the Youngsville council on April 10, 2025, as a phased plan for about 1,600 homes on Chemin Metairie Parkway south of the Youngsville Sports Complex. Its developers described a buildout of 20 to 25 years.
Where can I follow these projects? The City of Youngsville posts council agendas and agenda packets, including preliminary plats, on its website, and the Lafayette Parish Council publishes its agendas through Lafayette Consolidated Government. Our Youngsville neighborhood page has a broader view of the town.
If you are weighing a home or homesite near Guillot, Austin or Piat Road, Sylvia McLain and Cody Musgrove can help you find out what is filed on the land around it and how a nearby build-out could affect your plans. If you already own near one of these sites, a current home valuation is a good place to start. Let's Connect.